ALGORITHM FOR REDISTRIBUTING RESOURCES TO OPTIMIZE THE CURRENT WORK SCHEDULE

Received: 22.02.2024 Accepted: 29.02.2024 Published: 15.01.2024

DOI: 10.22394/1997-4469-2024-64-1-211-220

Full text

Abstract

Relevance of the topic. In a dynamically changing economy, project activities are an important area of development for any enterprise seeking to increase its competitiveness. Modern projects, as a rule, have a complex and branched structure, which is a set of work (tasks, subprojects) performed sequentially or in parallel. Managing such projects in an unstable and changing market situation is quite a difficult task. Target. Development of a genetic algorithm for redistributing labor resources between individual works and attracting subcontracting resources to optimize the current project schedule. Methodology. The study was carried out based on mathematical modeling methods. Results and conclusions. Software developed on the basis of a genetic algorithm for redistributing labor resources between individual works and attracting subcontracted resources allows you to automate the process of redistributing your own and subcontracted resources to minimize additional costs for project implementation. Application area. The scope of development of the enterprise's project activities. Key words: project, network graph, control points, critical path, project deadline, deviation management, genetic algorithms.

Keywords

Received: 22 February 2024 · Accepted: 29 February 2024

How to cite

Для цитирования:

Азарнова Т.В., Подвальный Е.С., Аснина Н.Г., и др. АЛГОРИТМ ПЕРЕРАСПРЕДЕЛЕНИЯ РЕСУРСОВ ДЛЯ ОПТИМИЗАЦИИ ТЕКУЩЕГО КАЛЕНДАРНОГО ПЛАНА ВЫПОЛНЕНИЯ РАБОТ // Регион: системы, экономика, управление. 2024. Т. 1, № 1 (64). С. 211–220. https://doi.org/10.22394/1997-4469-2024-64-1-211-220

For citation:

Azarnova T.V., Podvalny  E., Asnina  N., et al. ALGORITHM FOR REDISTRIBUTING RESOURCES TO OPTIMIZE THE CURRENT WORK SCHEDULE // Region: Systems, Economics, Management. 2024. Vol. 1, no. 1 (64). P. 211–220. https://doi.org/10.22394/1997-4469-2024-64-1-211-220

How to Cite

Azarnova T.V., Podvalny  E., Asnina  N., et al. ALGORITHM FOR REDISTRIBUTING RESOURCES TO OPTIMIZE THE CURRENT WORK SCHEDULE // Region: Systems, Economics, Management. 2024. Vol. 1, no. 1 (64). P. 211–220. https://doi.org/10.22394/1997-4469-2024-64-1-211-220

References

  1. Ballestín F. R. Leus (2009) Resource-constrained project scheduling for timely project completion with stochastic activity durations / F. R. Ballestín // Production and Operations Management. — Vol. 18. — Pp. 459—474.
  2. Berthaut F. Time-cost trade-offs in resource-constraint project scheduling problems with overlapping modes / F. Berthaut, R. Pellerin, N. Perrier, & A. Hajji // International Journal of Project Organisation and Management. — 2014. — 6 (3). — 215—236.
  3. Choi B. C. A continuous time-cost tradeoff problem with multiple milestones and completely ordered jobs / B. C. Choi, & M. J. Park // European Journal of Operational Research. — 2015. — 244 (3). — 748—752.
  4. Hillier F. Introduction to Operations Research / F. Hillier, & G. J. Lieberman // Penn Plaza. — New York, NY, 2015. — 10121.
  5. Liu Z. Resource-constrained multiple projects scheduling with the objective of minimizing activities cost / Z. Liu, & Y. Zheng // In 2008 Chinese Control and Decision Conference. — 2008. — July. — Pp. 1027—1032.
  6. Lu W. Research into the moderating effects of progress and quality performance in project dispute negotiation / W. Lu, J. Liu // International Journal of Project Management. — 2014. — 32 (4). — Pp. 654—662.
  7. Martens A. The impact of applying effort to reduce activity variability on the project time and cost performance / A. Martens, M. Vanhoucke // European Journal of Operational Research. — 2019. — Vol. 277. — Pp. 442—453.
  8. Mahmoudi A. Project scheduling by incorporating potential quality loss cost in time-cost tradeoff problems: The revised KKH model / A. Mahmoudi and S. A. Javed // Journal of Modelling in Management. — 2020. — Vol. 15, No. 3. — Pp. 1187—1204.
  9. Trietsch D. PERT 21: Fitting PERT/CPM for use in the 21st century // D. Trietsch, K. R. Baker // International Journal of Project Management. — 2012. — Vol. 30, Issue 4. — Pp. 490—502.
  10. Азарнова Т. В. Алгоритм управления временными параметрами выполнения проекта на основе системы контрольных точек / Т. В. Азарнова, Е. В. Иванова // Вестник Воронежского государственного университета. Серия: Системный анализ и информационные технологии. — 2022. — № 4. — С. 39—51.
  11. Ballestín F. R. Leus (2009) Resource-constrained project scheduling for timely project completion with stochastic activity durations / F. R. Ballestín // Production and Operations Management. — Vol. 18. — Pp. 459—474.
  12. Berthaut F. Time-cost trade-offs in resource-constraint project scheduling problems with overlapping modes / F. Berthaut, R. Pellerin, N. Perrier, & A. Hajji // International Journal of Project Organisation and Management. — 2014. — 6 (3). — 215—236.
  13. Choi B. C. A continuous time–cost tradeoff problem with multiple milestones and completely ordered jobs / B. C. Choi, & M. J. Park // European Journal of Operational Research. — 2015. — 244 (3). — 748—752.
  14. Hillier F. Introduction to Operations Research / F. Hillier, & G. J. Lieberman // Penn Plaza. — New York, NY, 2015. — 10121.
  15. Liu Z. Resource-constrained multiple projects scheduling with the objective of minimizing activities cost / Z. Liu, & Y. Zheng // In 2008 Chinese Control and Decision Conference. — 2008. — July. — Pp. 1027—1032.
  16. Lu W. Research into the moderating effects of progress and quality performance in project dispute negotiation / W. Lu, J. Liu // International Journal of Project Management. — 2014. — 32 (4). — Pp. 654—662.
  17. Martens A. The impact of applying effort to reduce activity variability on the project time and cost performance / A. Martens, M. Vanhoucke // European Journal of Operational Research. — 2019. — Vol. 277. — Pp. 442—453.
  18. Mahmoudi A. Project scheduling by incorporating potential quality loss cost in time-cost tradeoff problems: The revised KKH model / A. Mahmoudi and S. A. Javed // Journal of Modelling in Management. — 2020. — Vol. 15, No. 3. — Pp. 1187—1204.
  19. Trietsch D. PERT 21: Fitting PERT/CPM for use in the 21st century / D. Trietsch, K. R. Baker // International Journal of Project Management. — 2012. — Vol. 30, Issue 4. — Pp. 490—502.
  20. Azarnova T. V. Algorithm for controlling the time parameters of the project based on a system of control points / T. V. Azarnova, E. V. Ivanova // Bulletin of the Voronezh State University. Series: System Analysis and Information Technologies. — 2022. — No. 4. — Pp. 39—51.